CHAPTER 01The opportunity
Conceptual editorial image of a coal conveyor crossing a mining landscape
MPUMALANGA · PROPOSED 10-YEAR CONVEYOR BOOT · RESEARCH UPDATE OCT 2026

A 6 km pit-to-plant conveyor. Bankable only if the floor is.

Triad Mining and Logistics is seeking a capital partner to fund, build, own and operate a proposed approximately 6 km overland coal conveyor at Arnot under a ten-year BOOT service contract, before transfer to the mine. At R30/t on 300,000 t/month it earns R108m a year at full volume. Against the R397m funding requirement, that is about 27% of the capital each year. Whether it carries debt depends on the minimum payment, the mine’s credit and a capex that funders can verify.

Development-stage proposal. All figures are client terms, research estimates or arithmetic on them, and remain subject to technical, commercial, credit and legal due diligence.

Illustrative conveyor imagery · Not the Arnot route
02 / THE HEADLINE ARITHMETIC

The engineering is modest. The floor, the counterparty and the capex decide.

At R30/t on 300,000 t/month the conveyor earns R108m a year at full volume — 27.2% of the client’s R397m BOOT funding requirement. Use the rate toggle below to move the tariff up or down from R30/t. Whether that cash flow can carry debt depends almost entirely on how the minimum monthly payment is defined.

Client rate
R/t

R1 steps, or type a value from R15 to R50. The rate applies to every calculation on this page.

ItemValueBasis
Base revenueR9.0m/month · R108.0m/yrR30.00/t × 300,000 t/month (client terms)
Revenue vs funding27.2% of R397m a yearFull-volume revenue as a share of the funding requirement
Contracted minimum (floor)R4.5m/month · R54.0m/yr150,000 t/month (50% of design) × R30.00/t, paid whether or not coal is conveyed
Capex benchmarkR110–330m for 6 kmEUR 1–3m/km vendor guidance
Client funding requirementR397m · ≈R66m/kmIncl. IDC, fees, Eskom connection, contingency
Simple payback on R397m≈4.8 yrs at base · ≈13.7 yrs at 50%R25m/yr indicative opex
Senior debt cost10.25–11.75% floatingJIBAR 7.25% + 300–450 bps
DSCR at 60% gearing (R238.2m), 11%2.05x at 100% · 0.72x at 50% floorDebt service R40.4m/yr; lenders need 1.2–1.4x
Rate for the 50% floor to carry debtR36.36/t at 1.0x · R40.85/t at 1.2xTariff at which the floor alone covers debt service
Time to first coal27–35 months15-month build + permitting
01 / 03

Ready to test

The tariff sits inside the R25–R40/t trucking band, the asset is physically modest and the 2026 cost of capital is knowable.

02 / 03

Not yet bankable

The 150,000 t/month floor covers only about 0.72x of debt service, the mine counterparty is unproven and R397m sits above international installed-cost guidance.

03 / 03

What would change it

A rand-denominated monthly capacity charge — at R397m and R30/t, about 70% of base revenue covers debt service at 1.2x — credit support linked to the mine’s offtake chain and capex confirmed by OEM budget quotations.

Important context / Revenue figures are arithmetic on the client’s tariff and capacity. Opex, capex and rate inputs are indicative research values, not contracted terms.

03 / THE MINE’S BUSINESS CASE

R30/t sits inside the trucking band and removes diesel risk.

No published short-haul coal trucking tariff exists for the area, so the comparison is built bottom-up: truck running costs of R12–15/t, front-end loader loading of R8–12/t and roads, dust, weighbridge and supervision of R5–10/t give an indicative all-in R25–R40/t over 6 km in 2026 rand.

MINE COMPARISON

Conveyor tariff vs trucking the same 6 km

Client rate
R/t
R/t
R/t
Mtpa
R15/tTrucking band R25–40/tR45/t
R9.0mAnnual saving to the mine
R2.50/tDifference per tonne
R5.00Tariff per tonne-km (global benchmark ≈R1.8/t·km)

Indicative 2026 trucking build: truck R12–15/t + loading R8–12/t + roads, dust and supervision R5–10/t. Operator quotes are still required.

01 / 03

Diesel volatility

Inland wholesale diesel reached a record R31.95/l on 7 October 2026. A conveyor tariff indexed to CPI and electricity removes that exposure from the mine’s cost base.

02 / 03

Haul traffic

Roughly 290 side-tipper loads a day of on-site traffic, haul-road upkeep and dust are avoided. Public-road externalities matter only if the truck route uses public roads.

03 / 03

The honest caveats

Carbon savings are thin on Eskom’s grid, and R30/t is about 2.8 times the global all-in benchmark of R10.5–11/t for 6 km. The tariff must be defended bottom-up.

Important context / The pitch must rest on risk transfer rather than headline saving: against low-cost trucking, R30/t is roughly break-even; against high-cost trucking, the mine saves up to about R36m a year.

04 / THE PHYSICAL ASSET

Size the conveyor for the tonnes the tariff actually pays for.

The EOI (TCE-OLC-EOI-001 Rev 02, closing 29 October 2026) is collecting OEM rough-order estimates at 1,000, 1,250 and 1,500 t/h. Its 848 t/h average requirement on a 26-day, 16-hour, 85% calendar means 1,000 t/h is already about 85% utilised.

PITPit sources & ROM feed
LOADLoading & stockpile
CONVEY≈6 km overland · 1,000–1,500 t/h
PLANTReceiving plant
POWER Eskom supply ≈4 km from route · NMD increase on the mine’s supply or self-build
01 / 04

01 / Feed interface

Validate pit sources, coal characteristics, loading method and stockpile capacity against a ten-year mine plan.

02 / 04

02 / Corridor

Complete survey, ground investigation, watercourse crossings and registered servitudes along the 6 km route.

03 / 04

03 / Power

No power on route; Eskom supply is about 4 km away. Connection route, cost and timing are a capex and schedule item.

04 / 04

04 / Capacity headroom

1,250 or 1,500 t/h buys expansion headroom that R30/t on 300,000 t/month does not pay for unless the mine commits to more tonnes.

Important context / The visual here is a conceptual interface diagram, not a surveyed alignment or approved route. No route drawing is included in this site.

05 / COST BENCHMARKS

R397m must be reconciled line by line before funders trust it.

The client’s R397m funding requirement equals about R66m/km all-in. International vendor guidance of EUR 1,000–3,000 per metre implies R110–330m installed for 6 km. The remaining R67m or more must be explained by the Eskom line, interest during construction, fees and contingency.

CAPEX BENCHMARKS · R MILLION

Where R397m sits against the evidence

Belt, two 6 km strands
R37m
Civils, flat 6 km route
R36–72m
Vendor installed guidance
R110–330m
EPC band, 1,500 t/h steel-cord
R250–400m
Client funding requirement
R397m

Reconcile the R397m

Enter what the client can evidence. Anything left over is unexplained until a line-item breakdown is supplied. At the EPC-band midpoint plus 20% contingency, only about R7m of R397m is left for the Eskom line, IDC and fees.

R m
% of EPC
R m
R m
EPCContingencyEskom lineIDC & feesUnexplained

R7.0m of R397m is still unexplained

No Eskom per-kilometre line price is published; obtain a Cost Estimate Letter (fee R36,056 excl. VAT). Eskom and IDC inputs start at zero because no sourced figure exists.

01 / 03

Estimate accuracy

At EOI stage, civils are AACE Class 5 (−20/−50% to +30/+100%) and mechanicals at best Class 4. Show a −20%/+30% band and 15–25% contingency.

02 / 03

Energy

Eskom Megaflex 2026/27 blends to about R2.35/kWh for a flat load. At 1.4–2.0 kWh/t that is R1.4–4.7/t, or R5–17m a year at 3.6 Mtpa.

03 / 03

Total cash opex

No sourced SA benchmark exists for maintenance, insurance or crew. The planning figure is R20–30m a year (R5–10/t); R25m is used here.

Important context / Belt life on clean-coal steel-cord duty is plausibly 10–15 years, so a mid-life replacement falls largely after handover. Electrical long-leads (40–80 weeks) are the documented procurement bottleneck.

06 / REVENUE SECURITY

Lenders size debt off the contracted floor, not the base case.

The client’s minimum payment is 150,000 tonnes a month — half the 300,000 t design — paid at the tariff whether or not the coal is conveyed. At R30/t that is R4.5m a month, or R54m a year. After R25m of opex it covers only about 0.72x of debt service at 60% gearing on R397m. Test how a higher floor or a capacity charge changes debt capacity.

DEBT CAPACITY BY FLOOR

How much senior debt each floor can carry

R397m funding at R30.00/t, R25m/yr opex, 11% over ten years. Dashed line: 60% gearing (R238.2m).

Client rate
R/t
25% tonnage floor
R9.8m · 2%
Client floor: 150,000 t/month (50%)
R142.3m · 36%
75% minimum volume
R274.8m · 69%
90% capacity charge
R354.3m · 89%
100% take-or-pay
R407.3m · 103%
Floor structureMinimum revenue / yrFloor cash after opexDSCR at 60% gearing
25% tonnage floorR27.0mR2.0m0.05x
Client floor: 150,000 t/month (50%)R54.0mR29.0m0.72x
75% minimum volumeR81.0mR56.0m1.38x
90% capacity chargeR97.2mR72.2m1.79x
100% take-or-payR108.0mR83.0m2.05x

Precedents: Transnet coal-line contracts are ten-year take-or-pay; Grindrod’s Matola terminal used a 75% minimum. The recommended structure is a fixed monthly capacity charge in rand, payable on availability, plus a variable R/t fee.

Important context / The 150,000 t/month minimum must be drafted as an enforceable take-or-pay obligation, payable on availability and matched to the mine’s offtake term, before any funder engagement.

07 / THE COUNTERPARTY

A floor is only as good as the party paying it.

The single largest exposure a funder will underwrite is the mine. Junior Mpumalanga collieries with ten-year Eskom contracts have entered business rescue within 14 months of signing, and five Highveld power stations are scheduled to close in 2030 — year four of the tariff.

01 / 03

Track record

Arnot OpCo signed a ten-year, conveyor-fed Eskom coal supply agreement in August 2021 and was in business rescue by October 2022. Vanggatfontein, Optimum and Tegeta followed similar paths.

02 / 03

Reserves

Banks lend against Proved, not Probable, reserves. A “30+ year life of mine” claim is atypical for the Witbank field; ten years at 3.6 Mtpa needs about 36 Mt.

03 / 03

Throughput reality

A Witbank case study showed plant yields 25–54% below geological prediction. Test P50/P90 at 70–85% of nameplate and wet-season quarters at 75–85%.

To 2030

Years 1–4

Relatively secure demand: Eskom burnt 96.5 Mt in FY2026 and API4 was $127.95/t on 27 Oct 2026.

2030–2034

Years 4–8

The cliff: Camden, Hendrina, Grootvlei, Arnot and Kriel (≈7.4 GW) slated to close in 2030. Slippage is plausible but not lendable.

2034+

Years 8–10

Depends on the receiving station (Kendal, Kusile, Duvha, Matla, Tutuka run past 2034), third-party rail access and reserves.

Important context / Arnot power station is one of the five Highveld stations slated for 2030 retirement. The receiving station and offtake for this mine’s coal must be identified before any post-2030 revenue is relied on.

08 / TEST THE CASE

Is this worth considering? Test it before anyone commits.

Toggle the tariff up or down from R30/t, then change volume, floor structure, capex, financing and term. Seven screening tests show the investor and the mine, in plain terms, whether the case is worth progressing to a full model.

R397m, 50% tonnage floor, ten-year term, research debt terms.

Tariff

Client rate
R/t

R1 steps, or type a value from R15 to R50. The rate applies to every calculation on this page.

Minimum payment structure

% of design tonnes

Client terms: a minimum of 150,000 t/month (50% of design), paid at the tariff whether or not the coal is conveyed.

Volume

t/month
% of design
% of design

Cost

R million
R million/yr
% p.a.

Financing

% of funding
%
years
x
%

Term & mine alternative

years
R million
R/t
EARLY SCREENING SIGNALNot yet bankable on these assumptions

1 screening test fail. Change the structure or close the evidence gaps before taking this case to funders.

  • Fail
    Contracted floor covers debt service0.72x
    Funder · Pass ≥ 1.20x · watch ≥ 1.00x
  • Pass
    Scenario minimum DSCR2.05x
    Funder · Pass ≥ 1.30x · watch ≥ 1.00x
  • Pass
    Equity IRR clears hurdle23.6%
    Funder · Pass ≥ 20% · watch ≥ 15%
  • Pass
    Project IRR above debt cost16.3%
    Funder · Pass ≥ 13.0% · watch ≥ 11.0%
  • Pass
    Simple payback inside contract term4.8 yrs
    Both · Pass ≤ 8.0 yrs · watch ≤ 10 yrs
  • Pass
    Conveyor cheaper than trucking for the mineR30.00/t vs R32.50/t
    Mine · Pass ≤ trucking · watch ≤ trucking + 10%
  • Watch
    Capex intensity within benchmarkR66m/km
    Both · Pass ≤ R55m/km · watch ≤ R80m/km
R108.0mRevenue, year 1
R83.0mCash before debt service, year 1
R54.0mContracted minimum revenue / yr
R40.4mDebt service on R238.2m
R142.3mDebt the floor supports · 36% gearing
R9.0mMine saving vs trucking / yr

The client model reports a 16.2% project IRR and 23% equity IRR. At R397m and R30/t this simplified ten-year model gives about 16.3% and 23.6% at full volume with no indexation — close to the client’s figures. Confirm the client model’s term, tax and residual-value assumptions.

Annual cash flow vs debt service

RevenueCash before debt serviceDebt service

Bars in red fall below 1.00x debt service. Year 5 is calendar 2030 if commercial operations start in 2026; first coal is realistically 27–35 months from a decision, which moves the cliff earlier in the term.

Sensitivity: tonnage floor × funding requirement

Floor / chargeR330mR397mR437mR476m
50%0.86x0.72x0.65x0.60x
75%1.67x1.38x1.26x1.15x
90%2.15x1.79x1.62x1.49x
100%2.47x2.05x1.86x1.71x

All other assumptions as currently set, including the R30.00/t tariff. R330m is the top of vendor installed-cost guidance; R397m is the client’s funding requirement; the last two columns add 10% and 20% overruns.

Tariff sensitivity: rate up or down from R30/t

TariffRevenue / yrMinimum revenue / yrFloor DSCRMinimum DSCREquity IRRMine saving / yrSignal
R90.0mR45.0m0.49x1.61x8.8%R27.0mFail
R99.0mR49.5m0.61x1.83x16.6%R18.0mFail
· client · selectedR108.0mR54.0m0.72x2.05x23.6%R9.0mFail
R117.0mR58.5m0.83x2.27x30.1%R0.0mFail
R126.0mR63.0m0.94x2.50x36.4%R-9.0mFail
R144.0mR72.0m1.16x2.94x48.5%R-27.0mFail

All other assumptions as currently set. Select a rate to apply it across the deck.

Important context / Simplified annual, pre-tax screening model. Excludes tax, VAT timing, reserve accounts, construction-period interest beyond what is in capex, and residual value unless a transfer payment is entered. Not a forecast, tariff offer or investment recommendation.

09 / WHO WILL LEND, AT WHAT PRICE

The 2026 funding window is narrow, but open.

No South African bank policy excludes logistics infrastructure serving an existing mine. The realistic funder universe for a ticket of about R400m is the IDC (if the coal feeds Eskom), Afreximbank co-finance, structured lending to a creditworthy sponsor, OEM vendor finance, trader prepayments and mezzanine slices.

01 / 04

IDC

Continues to support coal feeding existing power stations on energy-security grounds; US$8bn Afreximbank partnership names mining and infrastructure. Support is conditional — it withdrew from Boikarabelo in 2020.

02 / 04

Relationship banks

Policies close new thermal mines but not logistics for existing mines. Nedbank and Standard Bank cap coal exposure at 0.5–1% of book; corporate or structured lending to a creditworthy sponsor is likelier than limited-recourse SPV debt.

03 / 04

OEM & vendor finance

Precedent: Komatsu Financial’s US$113m fleet facility for Boikarabelo.

04 / 04

Traders & mezzanine

Commodity traders have played a big role in structured coal funding; mezzanine funds such as Kholo can provide R50–200m slices at 16–20%.

Cost of capitalRateBasis
Repo rate7.25%After 25 bp hike, 23 Sep 2026
Prime10.75%From 25 Sep 2026
3-month JIBAR7.25%October 2026
10-year government bond8.73%October 2026
Senior debt (floating)10.25–11.75%JIBAR + 300–450 bps
Senior debt (fixed)11–13%Swap curve still to be retrieved
Mezzanine16–20%SA mezzanine targets
Equity hurdle18–25%Nominal rand, single-offtaker coal logistics

What lenders will ask for

  • Debt tenor 8–9 years inside the ten-year contract, sculpted to the capacity charge
  • Minimum DSCR 1.2–1.4x; 1.5–1.7x in downside tests; LLCR 1.7–2.0x
  • Six-month DSRA plus three-month maintenance reserve
  • Cost-overrun facility of 5–10% of capex
  • Interest-rate hedging or a fixed tranche
  • Independent engineer, EPC liquidated damages and performance bonds
  • Direct agreement with the mine and tripartite acknowledgement from Eskom or the export buyer
  • Mine collection account held with a major SA bank

Important context / REIPPPP achieved 70.8% gearing and 10.2% senior debt, but with a sovereign-backed 20-year offtake and no volume risk — a floor, not a benchmark. No third-party tariff-based conveyor BOOT was found in SA or the region for 2018–2026, so funders will price this as bespoke structured credit.

10 / THE PROPOSED TRANSACTION

Build. Own. Operate. Transfer — as a services contract.

A dedicated project company would fund, own and operate the conveyor and charge the mine a tolling fee. The mine must retain all mining decisions, remain the MHSA employer and licence holder, so nothing is “let or sublet” under MPRDA s11.

FundersSenior debt · mezzanine · equity
Project companyOwns the conveyor · holds project contracts
Mining clientCapacity charge + R/t fee · feed · permits as right holder
↓   contracted delivery and operations   ↓
Triad Consulting EngineersEngineering & project management
Appointed OEMFixed-price EPC · LDs · bonds
Triad Mining & LogisticsOperations & maintenance

The project company owns and operates the conveyor and charges the mine a tolling fee, secured by cession of coal receivables, a debt-service reserve and lender step-in rights.

01 / 03

Security package

Cession of coal receivables into a lender-controlled account, a six-month debt-service reserve (about R20m on 60% gearing of R397m), parent guarantees, cross-default and lender step-in.

02 / 03

Handover

Lenders give no credit to post-contract value. Full recovery by year 8–9, or a credit-supported transfer price or termination payment at least equal to outstanding debt.

03 / 03

Tax

A non-right-holder cannot safely rely on the s36 100% allowance. Model s11(e) wear-and-tear with s12C as upside; avoid a lease structure (s23A); 15% VAT with a construction VAT bridge.

Important context / Project company ownership, debt and equity participation, security rights and transfer terms remain to be agreed. No equity allocation is offered here.

11 / THE CRITICAL PATH

Permitting, not fabrication, sets the date of first coal.

The EOI’s 15-month build is credible, but the s102 amendment, NEMA Basic Assessment, water-use authorisation, servitudes and an Eskom connection put first coal 27–35 months from decision. Only the mining-right holder can lodge the applications.

M0M6M12M18M24M30M36
Pre-application & studies M0–M2DMPR, DWS and SAHRA meetings; specialist studies; Eskom load application; landowner engagement.
M0–M2
Applications & participation M2–M4Draft BAR/EMPr amendment and WULA; 30-day and 60-day public participation; s102 lodged and accepted.
M2–M4
Statutory decisions M4–M11197-day BA clock to EA and s102 approval; WUL decision; SAHRA comment. Backlog pushes this to months 12–18.
M4–M11
Appeals & land rights M11–M14Appeal window; servitudes registered; wayleaves; dust plan approved; Eskom quote accepted or self-build signed.
M11–M14
15-month build M12–M27From first manufacturing release; electrical long-leads (40–80 weeks) ordered at financial close.
M12–M27

First coal → month 27

Conditions precedent to drawdown should include a final unappealed EA and s102 approval, WUL or GA registration, registered servitudes, an Eskom supply agreement, an approved dust plan and a tripartite direct agreement with the mine.

Important context / Durations combine statutory clocks with observed backlogs. Early works that need no environmental authorisation can start around month 6 at the sponsor’s risk.

12 / ACCOUNTABILITY

Clear responsibility from design to dependable service.

Triad Consulting Engineers is proposed to lead design, project management and construction management, with an appointed OEM executing the works and Triad Mining and Logistics operating the conveyor for the project company.

01 / 04

Triad Consulting Engineers

Design basis, multidisciplinary engineering, procurement support, controls, supervision and handover.

02 / 04

Appointed OEM

Supply, construct and commission under a fixed-price EPC with liquidated damages and performance bonds.

03 / 04

Triad Mining & Logistics

Operate and maintain to agreed availability standards, under the mine’s conveyor Code of Practice (GN R1024) with SANS 971 belting.

04 / 04

Independent engineer

Funder-appointed review of design, budget, progress and acceptance. Availability guarantees should carve out s54 stoppages not caused by the operator.

Important context / EPCM and OEM obligations would be contracted separately. A single fixed-price completion guarantee is not established.

13 / WHAT A CREDIT PAPER WILL ASK

Match each material risk with evidence and a mitigant.

Risks ranked by their likely weight in a funder’s credit paper. Rankings are the research author’s judgement from the cited evidence, not measured frequencies.

14 / BEFORE APPROACHING FUNDERS

Close the data gaps before a funder sees the case.

Use this checklist with the mine to track what is known. Each item is something the current documents do not yet say, and that a funder or independent engineer will ask for.

0 OF 17 CONFIRMED · 0%Not ready to approach funders

Close the client-number and mine-offtake gaps first — they decide bankability.

Client numbers
Mine & offtake
Permits & legal
Market data
Ticks stay on this screen only and are not saved or sent.

Source register

15 / PARTNER WITH TRIAD

From “is R30/t enough?” to “who guarantees how much of it?”

Presented as a two-party commitment — with the mine’s permitting and floor obligations drafted as tightly as the funder’s build obligations, and the R397m confirmed by an EPC budget quotation — the deal fits the 2026 window the IDC, Afreximbank and relationship banks have left open for logistics serving existing coal supply.

01 / 02

The discussion now

Development funding appetite, preferred floor structure, credit support from the mine’s offtake chain and the partner’s diligence process.

02 / 02

The first decision

Fund a development stage to obtain OEM pricing, permitting, a confirmed floor and a full model — then decide on delivery funding.

Important context / This is an indicative, non-binding invitation to discuss the project. No funding commitment or securities offer is made.

Investor and mine questions